Building Your Home in Togo: From Land to Key Handover
Listings, new developments and property professionals across Togo, Benin, Côte d'Ivoire, Senegal and Ghana.
20 November 2026
6 min
· Rédaction Imonga
Secure the land before drawing any plan
Building starts with checking that the plot can legally host a structure. Decree n° 67-228 of 24 October 1967 bans construction on land that is "unfit for building, unstable, subject to erosion, flood-prone or insalubrious". Check also that the parcel is not in a servitude zone or an unapproved subdivision. The land status in Togo distinguishes several levels of security: the land title remains the only document that allows the sale or exchange of land. Law n° 2018-005 of 14 June 2018 establishing the Land and Domain Code introduced the land booklet to recognise customary rights, but this document does not serve as a transfer title.
Have a boundary survey carried out by a sworn surveyor before you buy. The operation materialises the limits and reveals any overlaps. If the seller only produces a promise or a receipt, demand instead the notarised deed or the land title. To avoid a double sale, check the land registers at the Directorate General of the Cadastre.
Architect, plans and budget
Decree n° 2016-043/PR of 1 April 2016 regulates the issuing of urban planning documents. It defines the project owner (you), the architect and the surveyor. For permits in categories A, B and C, the involvement of an architect registered with the National Order of Architects of Togo (ONAT) is mandatory. The architect prepares the location plan at 1/5,000 scale, the site plan at 1/200 scale, the floor plans, the descriptive estimate and, depending on project size, a fire-safety notice or a geotechnical study.
The architect's fees are negotiable. Ask for a written quotation detailing the studies, the building-permit application and the number of site inspections included.
Obtain the building permit
The application is submitted online through the national platform via the Integrated Building Permit Management System (SIGPC). According to the service-public.gouv.tg portal, the processing time is 15 days, the tax is 100 FCFA per square metre of construction and the permit is valid for 4 years. The competent authority is the municipality or prefecture of the project location, with technical support from the Directorate General of Urban Planning and Housing.
The file must include a copy of the title deed (land title, registration certificate or notarised deed), dimensioned plans, UTM coordinates and, for an extension or renovation, a demolition plan. The permit fixes the exact location, height and appearance of the building. Any substantial change to the approved design requires a new application.
Start construction on time and to code
Decree n° 67-228 requires works to begin within six months of permit issuance. After that deadline the permit lapses. During construction, technical standards are enforced: each main room must be at least 10 m², ceiling height must be at least 2.80 m, corridors must be at least one metre wide, ventilation is compulsory and, above four storeys above ground level, a lift is required.
A 2018 order introduced technical control of construction works. Inspections cover structural strength, fire safety and accessibility. Keep all invoices, inspection reports and photographs: they will prove compliance on handover or resale.
From handover to key delivery
Before moving in, check that the completed works match the building permit and approved plans. Have a handover report drawn up with the contractor. If you bought the land and built directly, have the completion of works recorded by a notary to secure the value of the asset.
In the event of serious non-compliance (excess height, change of use, structural risk), the administration may order remedial works or even demolition at the builder's expense. Decree n° 67-228 explicitly states that a permit may be refused if the building would harm neighbouring interests or a listed monument.
Frequently asked questions
- Is an architect required for a family home in Togo? Yes, as soon as the project falls under categories A, B or C. Only an ONAT-registered architect can sign the plans and submit the file through the SIGPC. For advice on your specific situation, consult a notary or a lawyer.
- How much does a building permit cost? According to available information and the service-public.gouv.tg portal, the tax is 100 FCFA per square metre of construction. A 150 m² house therefore incurs 15,000 FCFA in permit fees, excluding architect fees and soil studies.
- How long does it take to get a permit? According to the service-public.gouv.tg portal, the legal deadline is 15 days from the submission of a complete file on the online platform.
- Can you build with only a land booklet? The public service requires a land title, a registration certificate or a notarised deed to issue a building permit. The land booklet recognises customary ownership but does not replace the title for transfer or construction in an urban zone.
- What is the risk of building without a permit? Erecting a structure without a planning authorisation is an offence. The administration may order work to stop, require compliance or order demolition. To assess the consequences in your case, consult a notary or a lawyer.
- How can the diaspora monitor a building site? Appoint a relative or surveyor for regular visits, demand weekly photo reports and keep all signed quotations. Our guide covers building from abroad.
Sources
- Decree n° 67-228 of 24 October 1967 on urban planning and building permits: ban on building on flood-prone or unstable land, technical standards (room size, height), six-month start deadline.
- Decree n° 2016-043/PR of 1 April 2016 regulating the issuance of urban planning documents: definitions of project owner, architect, surveyor and permit categories.
- Togo Public Service portal, "Obtention du permis de construire": 15-day processing time, cost of 100 FCFA/m², 4-year validity, list of documents, online SIGPC procedure.
- Law n° 2018-005 of 14 June 2018 establishing the Land and Domain Code: land registration system, recognition of customary land rights, boundary survey.
Read next
Building from the diaspora: how to track a construction site remotely in Togo
Building in Togo from abroad requires securing the land title, obtaining a building permit and contracting a certified architect. Remote tracking relies on weekly photo reports, video calls and stage-based payments.
Building permit in Togo: required documents and steps before breaking ground
Any new build, extension or demolition in Togo requires a building permit issued by the local municipality or prefecture. Documents, fees and timelines depend on whether your project is category A, B or C.
Real estate in Kara (Togo): rent, buy and secure land rights
Northern regional capital, Kara concentrates student and administrative rental demand. Here is how to rent or buy while securing land rights.
Flood-prone land in Togo: how to spot the risk before you buy
In Togo, Greater Lomé is chronically exposed to flooding. Here is how to check a plot before you buy: rainy-season visit, neighbours, town hall, surveyor.