Building permit in Togo: required documents and steps before breaking ground
Listings, new developments and property professionals across Togo, Benin, Côte d'Ivoire, Senegal and Ghana.
18 November 2026
8 min
· Rédaction Imonga
In Togo, any new construction, extension or demolition without rebuilding requires a building permit. This administrative decision is issued by the municipal or prefectural authority, with technical support from the General Directorate of Urban Planning and Housing. Applications are submitted online through the construireautogo.gouv.tg platform via the Integrated Building Permit Management System (SIGPC). The national portal lists a fee of 100 FCFA per square metre of built surface, but some municipalities charge a different rate; for example, the Mô 2 municipality charges 300 FCFA per square metre. The permit is valid for four years.
Legal requirement
The building permit requirement rests on Decree No. 67-228 of 24 October 1967 on urban planning and building permits in agglomerations. Article 25 of this text mandates a permit for any erection in an agglomeration required to have an urban plan, including outbuildings and fences. Decree No. 2016-043/PR of 1 April 2016 regulating the issuance of urban planning acts defines the permit as an administrative decision that explicitly or tacitly authorises new construction, modification of unfinished works, regularisation of unlawfully started works, or demolition without rebuilding. Article 24 of the same decree states that anyone wishing to undertake, install, modify, regularise or demolish without rebuilding a residential or non-residential construction, even without foundations, must first obtain this permit.
The three project categories
Inter-ministerial Order No. 726/MUHRF/MTPI/MATDCC classifies building permit projects into three categories based on height, size and number of occupants.
| Category | Risk | Examples |
|---|---|---|
| A | Low | Single-family or multi-family housing up to R+2 (height at most 8 m) for A1; R+3 (height below 15 m) or public establishments with fewer than 20 people for A2. |
| B | Medium | Buildings above R+4 and up to 50 m high; public establishments or workplaces receiving 21 to 300 people. |
| C | High | Public establishments or workplaces with more than 300 people; high-rise buildings; classified installations for environmental protection (ICPE). |
According to Inter-ministerial Order No. 726/MUHRF/MTPI/MATDCC, a geotechnical study is required for categories B and C, and for category A as soon as the building has more than one level. It is waived for a single ground floor or for an extension of less than 20 m² with no structural impact on the existing building.
Required documents
The national portal service-public.gouv.tg details the file composition by sub-category A1, A2, B1, B2 and C1 to C4. An architect certified and in good standing with the National Order of Architects of Togo (ONAT) is required.
For category A1, the file includes:
- legalised copy of the property title (land title, administration certificate, notarised deed or registration certificate);
- legalised copy of the applicant's identity document;
- descriptive estimate of the proposed works (drainage, sanitation, use of unbuilt spaces);
- situation plan at 1/5,000 or 1/10,000 scale with UTM coordinates;
- site plan at 1/200 scale;
- existing conditions plan of the site at 1/200 scale showing existing buildings and utilities;
- dimensioned floor plans at 1/100 or 1/200 scale;
- indicative structural plans (the A1 file remains a summary preliminary design).
Category A2 adds:
- structural plans drawn by an engineer registered with the National Order of Engineers of Togo (ONIT);
- a safety report prepared by an architectural firm in accordance with Order No. 1726/MUHCV/MSPC of 21 December 2017 on fire and panic safety measures in public establishments, high-rise buildings, classified installations and residential buildings;
- an affidavit from the ONIT-registered engineer.
Category B1 requires the A2 documents plus a report on measures for persons with reduced mobility (PMR). Category B2 adds geotechnical studies.
Category C progressively supplements the file:
- C1: site organisation report;
- C2: calculation note;
- C3: copy of the environmental compliance certificate issued by the minister in charge of the environment, pursuant to articles 38 and 39 of Law No. 2008-005 of 30 May 2008 on the environmental framework;
- C4: hazard study.
Application, fees and timeline
The request is submitted online on construireautogo.gouv.tg. SIGPC then notifies the fees to be paid. The national portal lists a cost of 100 FCFA per square metre and a processing time of fifteen days. In municipal practice, these figures vary: the Mô 2 municipality displays a rate of 300 FCFA per square metre and a timeline of sixty days. It is advisable to check with the municipality or prefecture of the site for the local fee and timeline. Payment is made before the final review of the application.
Validity and on-site obligations
The building permit is valid for four years from the date of issue. The beneficiary must display the authorisation on a rectangular white or yellow panel, legible from the public road for the entire duration of the works. The panel must show the company name or beneficiary's name, the permit date and number, the nature of the works, the authorised area and height, the address of the local authority where the file can be consulted, and the contact details of the control office. Inter-ministerial Order No. 1090/MUHCV/MSPC/MSPS/MATDCL of 16 August 2017 on the implementing arrangements of Decree No. 2016-043/PR also requires a declaration of works commencement and a declaration of completion. Failure to comply with these formalities exposes the owner to penalties.
On Imonga
Before starting construction, secure the land. Read our guides on buying land in Lomé and buying land in Kara. Although construction rules differ in neighbouring countries, the land verification steps remain essential everywhere.
Frequently asked questions
Do fences need a permit?
Yes, in Togo. Decree No. 67-228 of 24 October 1967 subjects fences to a building permit when they are erected in an agglomeration required to have an urban plan. For a specific case, it is advisable to consult a notary or a lawyer.
Can I build without an architect?
No. For categories A, B and C, the national portal requires an architect certified and in good standing with ONAT. The architect prepares the plans and certifies project compliance. If in doubt about your situation, a notary or a lawyer can guide you.
How long does it take to get a permit?
The national portal states fifteen days, but the Mô 2 municipality states sixty days. Timelines vary by municipality and file complexity.
Does a building permit prove land ownership?
No. In Togo, the permit is a planning authorisation, not a property right. You need a land title, administration certificate or notarised deed to prove ownership. To secure your position, consult a notary or a lawyer.
Is a geotechnical study required for a two-storey house?
Yes for category A as soon as there is more than one level, and for categories B and C, unless exempted under Inter-ministerial Order No. 726. A single ground floor is exempt.
What is the risk of building without a permit?
Works started without authorisation are unlawful. Decree No. 2016-043/PR provides for their regularisation under a permit, but also exposes the owner to administrative sanctions and a stop-work order. A lawyer can assist you in a regularisation process.
Building permit rules differ in Benin, Côte d'Ivoire and Ghana.
Sources
- service-public.gouv.tg : fee (100 FCFA/m²), timeline (15 days), validity (4 years), document list by category, online application through construireautogo.gouv.tg. Consulted on 18 November 2026.
- Inter-ministerial Order No. 726/MUHRF/MTPI/MATDCC : classification of categories A, B, C and sub-categories, geotechnical study rules. Consulted on 18 November 2026.
- Decree No. 67-228 of 24 October 1967 : building permit obligation in agglomerations (art. 25), fences and outbuildings. Consulted on 18 November 2026.
- Inter-ministerial Order No. 1090/MUHCV/MSPC/MSPS/MATDCL of 16 August 2017 : implementing arrangements of Decree 2016-043/PR, on-site display (art. 10 and 11), commencement and completion declarations. Consulted on 18 November 2026.
- Mô 2 municipality : local fee (300 FCFA/m²), local timeline (60 days), categories A and B issued by the municipality. Consulted on 18 November 2026.
Read next
Building from the diaspora: how to track a construction site remotely in Togo
Building in Togo from abroad requires securing the land title, obtaining a building permit and contracting a certified architect. Remote tracking relies on weekly photo reports, video calls and stage-based payments.
Easements and no-build zones in Togo: how to spot a risky plot before you buy
In Togo, a land title does not tell you whether you may build. Here is how to check building bans, the coastal public domain and flood-prone areas before you pay.
ACD in Togo: what buyers must check before purchasing land
The ACD in Togo does not authorize land sales. This customary document must lead to land registration, the only legal path for property transfer.
Buying property in Togo by power of attorney: precautions for the diaspora
Togolese diaspora members who buy property without travelling can grant power of attorney to a third party. Togo's Code foncier et domanial still requires strict formalities: prior registration, a notarised deed and an authentic power of attorney. Without these steps the deed is void and the funds are at risk.
Categories
From reading to searching
The advice above is worth most when applied to a specific property. 131 listings are online, viewable without an account.