Under construction
Apartment complex

111 K

Al-Bayt Al-Watani, Hayy Al-Rabi', Al-Tagammu' Al-Khamis, Le Caire, Egypt

From

EGP 1.5M

Floors

5

“From” price: the developer has not stated what it includes (VAT, notary fees, parking…).

About the project

Project 111 in the 4th district Al-Bayt Al-Watani Al-Tagammu' Al-Khamis located directly in front of Al-Ahly club

The 111 K project is located in the 4th district of Al‑Bayt Al‑Watani in Al‑Tagammu’ Al‑Khamis, directly in front of the Al‑Ahly club. The plot covers 604 sq m and the building consists of a basement, a ground floor and three repetitive upper floors. Construction began with excavation on 1 June 2022, followed by soil compaction the next day, then the pouring of foundations, basement columns and successive floor slabs up to the roof slab on 26 October 2022. Masonry work started on 30 November 2022 and the first phase of elevator installation took place on 21 December 2022. The developer Civic Residence has more than 20 years of experience in Egypt and Saudi Arabia.

  • Prime location directly in front of Al‑Ahly club
  • Developer with over 20 years of experience in Egypt and Saudi Arabia
  • Single owner of all projects
  • Elevator available
  • Significant construction progress

Payment plans available

Launched in 2022

Unit types & pricing

TypeBedsSizeFrom
Apartment——EGP 1.5M

Units in this development

1 units in total, 1 still available.

Price

EGP 1,500,000

Cheapest still on sale

EGP 1,500,000

unit L01 · Apartment · Available

UnitTypePriceStatus

L01

Apartment

EGP 1,500,000

Available

Prices and availability as provided by the developer. Confirm with them before committing.

No lot can be put on hold: the developer has not provided its building permit number, without which the country’s law prohibits any off-plan reservation.

Construction progress

The stages announced by the developer, and those actually completed.

0% complete

Phase de terrassement

planned June 2022

Overdue

Compactage du sol

planned June 2022

Overdue

Coulage fondations ordinaires

planned June 2022

Overdue

Coulage fondations armées

planned June 2022

Overdue

Coulage poteaux sous-sol

planned June 2022

Overdue

Isolation fondations

planned July 2022

Overdue

Fin remblai et début mur d'enceinte

planned July 2022

Overdue

Coulage dalles de circulation

planned July 2022

Overdue

Poteaux rez-de-chaussée

planned September 2022

Overdue

Dalle plafond 1er étage

planned September 2022

Overdue

Poteaux 2ème étage

planned September 2022

Overdue

Poteaux 3ème étage

planned September 2022

Overdue

Dalle plafond 3ème étage

planned October 2022

Overdue

Dalle toiture

planned October 2022

Overdue

Début travaux maçonnerie

planned November 2022

Overdue

Installation 1ère phase ascenseur

planned December 2022

Overdue

Dates as provided by the developer. Any gap between the planned and actual dates is shown here on purpose.

Amenities & features

Elevator

Gated

Parking

Project phases

  1. Phase de terrassement

    2022-06-01

  2. Compactage du sol

    2022-06-02

  3. Coulage fondations ordinaires

    2022-06-07

  4. Coulage fondations armées

    2022-06-20

  5. Coulage poteaux sous-sol

    2022-06-25

  6. Isolation fondations

    2022-07-02

  7. Fin remblai et début mur d'enceinte

    2022-07-06

  8. Coulage dalles de circulation

    2022-07-31

Location & surroundings

Devant le club Al-Ahly, Hayy Al-Rabi', Al-Bayt Al-Watani, Al-Tagammu' Al-Khamis

Club Al-Ahly

Al-Bayt Al-Watani

Al-Tagammu' Al-Khamis

Frequently asked questions about 111 K

How much does 111 K cost?

Prices shown on this page start at EGP 1.5M. The figure comes from the source cited at the bottom of the page: have the developer confirm it in writing before paying anything.

Who is building 111 K?

111 K is being developed by سيفيك ريزيدنس للتطوير العقاري. Their Imonga directory page lists their contact details and other developments.

Where is 111 K located?

111 K is located in Al-Bayt Al-Watani, Hayy Al-Rabi', Al-Tagammu' Al-Khamis, Le Caire, Egypt, at the stated address: Devant le club Al-Ahly, Hayy Al-Rabi', Al-Bayt Al-Watani, Al-Tagammu' Al-Khamis.

Can 111 K be paid in instalments?

This page mentions a payment plan. Its terms (down payment, duration, schedule) are negotiated with the developer: ask for them in writing.

Thinking of buying off-plan? Guarantees, payment schedule and risks: read our guide.

Developer

This developer's contact details are not shared. Write to them using the form below: they reply to you directly.

Learn more about this development

Your request is passed on to the developer, who replies to you directly. No commitment.

No need to create an account: your email address is enough. We send you a code to confirm it, you type it here, and your request is sent.

The reply will reach you at this address.

Free, no commitment. A 6-digit code is emailed to you to confirm your address; your details are only shared with your request.

Have a password? Sign in

Are you the developer of this project?

This listing was compiled from public sources. Claim it to correct the information, upload your brochure and receive buyer enquiries.

Claim this listing

More projects by سيفيك ريزيدنس للتطوير العقاري

136 K
Under construction

136 K

القاهرة الجديدة

From EGP 1.5M